Pull from VCS

  • Select a Data Store from the Data Stores list (The Data Store should ne Pushed at least once to the GIT repository).

  • Click the Pull from VCS icon for the selected Data Store.

  • The Pull from VCS dialog box appears.

  • The multiple uploaded versions of the Data Store with committed message for each version get listed as shown below:

    • Select: To select the version you want to pull.

    • Version: Version number only will list as V1, V2 etc.

    • Commits: This is to Identify the Data Store version Pulling from VCS (This is the message given while committing the data store push).

    • Commit Time – The date and time that Data Store is committed.

    • Committed By- The Username who committed the Data Store versioning.

  • Click the Pull option.

  • A confirmation message appears once the selected version of Data Store is pulled from the VCS.

Please Note: Once the user selects any version, the Pull option gets enabled.